KAI Carries Out Maintenance on 20,581 Railway Sleepers Throughout 2026
PT Kereta Api Indonesia (Persero) continues to carry out infrastructure maintenance to maintain the safety and reliability of train journeys. Throughout 2026 to date, KAI has implemented a maintenance program for 20,581 railway sleepers, consisting of 17,025 concrete sleepers and 3,556 synthetic sleepers across various operational areas.
This year, the concrete sleeper maintenance program covers 61,924 sleepers, with implementation reaching approximately 27.49 percent. Meanwhile, the synthetic sleeper program has been set at 16,839 sleepers, with 3,556 sleepers implemented, or approximately 21.12 percent.
Vice President Corporate Communication KAI Anne Purba said sleeper condition is one of the aspects considered in track maintenance because sleepers play a role in maintaining rail position and stability when trains pass over them.
“Infrastructure maintenance is carried out according to plan based on track condition inspection results. Sleepers that meet standards help maintain track geometry and rail stability so that train journeys can operate safely and reliably,” said Anne.
For concrete sleepers, one of the largest programs in 2026 is in Regional Division IV Tanjungkarang, covering 18,321 sleepers. To date, implementation has reached 9,390 sleepers, or approximately 51.25 percent of the program in that area.
The work is carried out gradually by considering material conditions, train traffic intensity, track inspection results, and the needs of each line. KAI also schedules work times so that maintenance activities can proceed while maintaining the smooth flow of train journeys.
“Travel safety depends greatly on the readiness of all infrastructure components. Therefore, inspections and maintenance are carried out regularly to ensure track conditions remain in accordance with operational standards and potential disruptions can be minimized from the outset,” said Anne.
Infrastructure maintenance also supports consistent travel punctuality. In September 2026, the on-time departure rate for passenger trains reached 99.71 percent, while the on-time arrival rate reached 97.45 percent. For freight trains, the on-time departure rate was recorded at 95.68 percent and the on-time arrival rate at 87.15 percent.
KAI regularly allocates specific work periods for track maintenance, both through track closures and intervals between train journeys. In September 2026, these activities were carried out across various Operational Areas in Java as part of periodic infrastructure maintenance work.
Anne added that sleepers are one of the various track components monitored regularly alongside rails, switches, bridges, and other supporting facilities.
“Track maintenance is work that takes place every day. The target is clear: to ensure infrastructure remains in proper and safe condition so that passenger journeys and freight transportation can operate safely, reliably, and on time,” concluded Anne.
VP Corporate Communication KAI